500 KV Double Circuit T/Line LILO Shikarpore (Line-2) gets energized

Netracon Technologies completes and Energizes 500 kV Double Circuit Over Head Transmission Line-II (an EPC Job under Contract SHK002) after availing shutdowns on connecting T/Lines which was pending due to system constraints. Length of the T/Line is 17 KM (appx) and is joining Guddu, Daddu and Shikarpur Grid Stations, Sindh. The Transmission line will help to increase system redundancy and stability of the National Grid. The Transmission line was completed 2 years earlier and we were waiting for shut down approval to get it connected with the National Grid. 500 KV Double Circuit T/Line (Line-1) has already been energized on May 15, 2016.