| Project Name | Quantity | Client/Contractor | Status |
| Erection of Towers & Stringing of 400 kV T/Line Line -A in Ethiopia - Africa. | 120 KM | EEPCO / KEC International | 99% Completed |
| Erection of Towers & Stringing of 330 kV Transmission Line Aboadze Thermal Plant to Volta SS Tema, Ghana - Africa | 215 km | Volta River Authority/ KEC Int'l | 98% Completed |
| National Load Control Center (NLCC) OPGW Various Locations in Afghanistan SubContract # IRP-10-09-041921-BV-AF-03 | 85 Km | USAID Afghanistan (Louis Berger Group Inc / Black Veatch)-Kabul | 75% Completed |
| Construction of IN & Out Arrangements of 110 kV T/ Line at Butkhak SS Afghanistan | 4 Towers | Siemens | 98% Completed |
| Construction of Foundations, Tower Erection, Stringing of Conductor and OPGW, Testing & Commissioning of 220 kV Double Circuit, Twin Bundle (ACSR Rail Conductor) Chashma-II Ludewala T/Line (Lot-II) | 65 Km | NTDC | 65% Completed |
| Supply, Installation, Testing & Commissioning of 132KV Switchyard for 225 MW Combined Cycle Power Plant - BHIKKI | job | ABB Pakistan | 82% Completed |
| Constrcution of Tower Foundations for 5.3 km, 11 kV T/Line From Khan Khwar Powerhouse to Weir / In Take Including Earthing | 5.3 km | WAPDA / NTDC | 98% Completed |
| Supply of Miscellaneous equipment, Erection and Civil Worksfor 132 kV GIS Hybrid Grid Station Gulistan-e-Johar(Hospital) Karachi | Job | ABB / KESC | 5% Completed |
| Project Name | Quantity | Client/Contractor | Status |
| 500 KV Labrador- San Manual( North Luzon-Philippines) Stringing Works | 23 Km | ABB SAE-SADELMI | 100% Completed |
| 500 KV San Manual-San Jose ( Luzon-Philippines) Stringing Works | 33.6 Km | NEIE | 100% Completed |
| Stringing of 230 Kv Labrador-Sual (North Luzon Project in Philippines) | 15 Km | ABB SAE-SADELMI | 100% Completed |