Netracon Technologies has outstanding capabilities in the field of construction / maintenance and storm restoration of Power Transmission Network. Over the years, we have gathered some of the most efficient transmission crews and personnel. Having a full range of in-house services has allowed Netracon Technologies to offer cost effective and value-added solutions to its customers.
Project In Hands
Collasp
Project Name Quantity Client/Contractor Status
Supply of Miscellaneous equipment, Erection of Equipment, Testing & Commissioning including Design & Construction of Civil Works for 132 kV GIS Hybrid Grid Station FTC Mehmoodabad, Karachi Job KESC / ABB 45% Completed Stopped due to Court Stay Order
Installation, Testing & Commissioning of Shekanbandar (SKB) 110 kV Switching Station (Northern Zone), Afghanistan. JOB KEC/MEW-Kabul in Progress
National Load Control Center (NLCC) OPGW Various Locations in Afghanistan SubContract # IRP-10-09-041921-BV-AF-03 108 Km USAID Afghanistan (Louis Berger Group Inc / Black Veatch)-Kabul 97% Completed
Installation, Testing & Commissioning of Sarepul (SPL) 110/20 kV Substation (Northern Zone), Afghanistan. JOB KEC/MEW-Kabul in Progress
Installation, Testing & Commissioning of Jalabadad (JLB) 110/20 kV Substation (Eastern Zone), Afghanistan. JOB KEC/MEW-Kabul in Progress
Installation, Testing & Commissioning of Mehtarlam (MHT) 110/20 kV Substation (Eastern Zone), Afghanistan. JOB KEC/MEW-Kabul in Progress
Installation, Testing & Commissioning of Imam Sahib (IMS) 110/20 kV Substation (Northern Zone) , Afghanistan. JOB KEC/MEW-Kabul in Progress
Installation, Testing & Commissioning of Taluqan (TLQ) 220/20 kV Substation (Northern Zone), Afghanistan. JOB KEC/MEW-Kabul in Progress
Testing & Commissioning, Civil & Local Works Telecom Equipment for KESC-2480-04B at 23 Grid Stations KESC / ABB In Progress
Tower Erection & Stringing of Double circuit, two conductors per phase, AAAC Aster Conductor, and 1 No. ACSR Skunk Earth wire & Stringing of 1 No. 48 Fibre OPGW for 225 kV Kribi - Mangombe Transmission Line Project in Cameroon 100 km KPDC / KEC Cameroon in Progress
Procurement of ELR Works for Transportation, Installation, Testing, Commissioning of Equipment & Civil Works of 132/11.5 KV Grid Station Plandri (conversion from 33 kV to 132 kV) Lot-III Bid No. IESCO/WB/PMU/GS/NCB-101 Job IESCO in Progress
Subcontract No. DEC-PJHP-S018, Engineering, Procurement and Construction of 132kV Double Circuit Overhead Transmission Line from the Jinnah Hydropower Project to Mari Grid Station (Daud Khel) JOB Dongfang Electric Corp. in Progress
Foundation & Piling Works at Rahim Yar Khan 500kV Transmission Line Project. JOB GAM Arak Ind. Co. in Progress
Collasp
Projects Completed
Collasp
Project Name Quantity Client/Contractor Status
500 KV Labrador- San Manual( North Luzon-Philippines) Stringing Works 23 Km ABB SAE-SADELMI 100% Completed
500 KV San Manual-San Jose ( Luzon-Philippines) Stringing Works 33.6 Km NEIE 100% Completed
Stringing of 230 Kv Labrador-Sual (North Luzon Project in Philippines) 15 Km ABB SAE-SADELMI 100% Completed