On instructions of Engr. Asghar Ali Sherazi MD NETRACON Technologies, Mr Ifzaal Humayun Construction Manager Karachi Projects personally took a Truck Load of Food items to a flood victim’s camp on Sajaval/Badeen Road near River Bridge & another camp at MAKLY. 260 food Packs were distributed to as much families with the help of coastal guards. Each Pack contained Flour 10KG Ghee , Sugar Daal Chana Daal Monng, Milk Pack each one Kg pack and a packet of Tea.
MD NETRACON Technologies, who is Chief Organiser Pakistan Engineering Association has sent PKR 100,000/- worth food items to a flood victims camp of Jackobabad area. The food items were delivered through Engr. Abdul Hai, Chief Organiser (PEA) Bluchistan.
MD NETRACON Engr Sherazi visited Gurdawara Panja Sahib at Hassan Abdal and purchased them Rs. 50, 000/- worth food items for the Langar to feed 200 person belonging to Hindu& Sikh minorities from the Swat & Jakobabad flooded areas. Hirendar Singh, administrator the sikh temple hailed the spirit of MD NETRACON Technologies Mr. Sherazi & prayed for him in evening prayers.
Engr. Asghar Ali Sherazi MD NETRACON Technologies has allocated PKR One Million to purchase food items for Deadliest Floods in Pakistan. Under this programme a truck food load (PKR 200,000/- ) was sent to SWAT area in Khyber Paktunkhwah, while another truck load of food items (worth PKR 350,000/-) was sent through FLP (http://www.flp.org.pk) to Chachran Sharif near Zahir Pir in Sadiqabad District in Punjab. FLP (Future Leader of Pakistan) is an organization of young people, who are providing social services & humanitarian assistance to the flood victims in all the four provinces with dedication & zeal.
People of all the four provinces of Pakistan are facing the deadliest floods of Pakistan's history which have left the country in tatters. It’s a calamity & disaster in the major part of the country. About one-fifth of the country — a chunk of land about the size of Italy — has been affected. More than 20 Million people have become homeless and are starving in different parts becoming islands. The effected population of the catastrophe is much larger than those who required humanitarian assistance after the 2004 Indian Ocean tsunami, the 2005 Kashmir earthquake and the 2010 Haiti earthquake combined.. The impact of the devastating floods is comparable to the partition in 1947 when 10 Million people crossed the newly created borders.The destruction of infrastructure & crops is estimated over $15bn .
Its is the time when each & every person of conscious around the world should rise up and play its role to help the victims of the catastrophe. . The humanitarian services always need the help & sponsorship from the people who can contribute a bit out of their fortunes.
In a panel discussion with Secretary IEP Engr. Amir Zamir, Engr. Naqvi & other eminent Engineers on importance of Kala Bagh Dam for Pakistan, Engr. Sherazi stressed on the technically viable Kala Bagh Dam. He further pointed out that Founder of Pakistan People’s Party Shahid Zulifqar Ali Bhutto wanted early construction of Kala Bagh Dam & during his tenure feasibility & final investigations were completed. He further emphasized the Gov’t to follow Mr Bhutto’s guidelines instead of reversing his decisions. He further told that these dams shave off the Flood Peaks, improves water regulation & compensates the power shortage.
NETRACON completes the civil Works of the Sixth 132 kV grid Station in Karachi.
ABB – Germany/Pakistan had awarded initially the job of construction of 132kV Grid Station at Gulshan-e-Maymar and Memon Goth to Netracon Technologies in March2008. It included design and construction of Civil Works, Erection of steel structures & Equipment, protection wiring and commissioning of Grid Station and 40 MVA power transformers. On commendable performance of the NETRACON Staff , the jobs of remaining works and finalization of the Grid Stations at PRL, Jail Road & Azizabad were handed over to NETRACON after failure of the other company to achieve the target and produce quality work. On recommendation of KESC & ABB Germany, the jobs were diverted to NETRACON Technologies. NETRACON fulfilled the expectations of the client and commissioned all the five Grid Stations as well as handed over to KESC.
The Site for the 6th Grid station was handed over to NETRACON in April,10 and NETRACON has already completed all the foundations and Double Storied RCC Structural Control House Building ( Size 36Mx12 M) . Erection of Steel Structures and Electrical Equipment has been taken in Hand.
NETRACON Technologies has already completed its assignment of completing Stringing of OPGW on the existing Line Section of 11kV Breshna Kot Kabul – Botkhak-Mahipar-Sarobi . The Job was awarded to NETRACON Technologies as turn key Project by LBG/B&V JV –USA under National Load Control Center Project (Lot-I). The Job included installation of OPGW on existing T/Line and testing of OPGW already strung. Installation of ODF at different Sub Station in various parts of Afghanistan was a part of the job too. However, the Job has been extended by including rectification of OPGW works done by M/S Symbions (USA) . All the substandard jobs carried out by Symbions USA are being rectified. The faulty stringing & sagging is being re-adjusted. The wrongly installed Tension Assemblies are being re-installed. Overall Progress of the work is 85%.
NETRACON Technologies have been awarded the job of Tower Erection & Stringing of 157 Km Long 220 kV Transmission Line from Pull e Khumeree - Kunduz – Sher Khan Bandar . The Transmission Line will help Afghanistan to import Power from Tajikistan. NETRACON Erection Crew has started its activities in July,2010 and has already erected more than 48 Towers by 21st August.
NETRACON Technologies has already completed its assignment of completing Tower Erection and Stringing of 225 Km long 330kV Aboadze – Volta Transmission Line in Ghana for KEC International. Volta River Authority (VRA) . The T/Line passes though very difficult terrene of Hilly , marshy & swampy lands. NETRACON efforts made the project get completed well in time. VRA Engineers & KEC Management has appreciated the efforts & efficiency of NETRACON Tech crews. NETRACON Stringing average was more than 20 Km P.M. MD NETRACON Technologies has congratulated Mr. Mehmood Alam & members of NETRACON Crew over their commendable performance. MD Netracon , Engr. Syed Asghar Ali Sherazi also approved a special bonus money amounting PKR 2 Million for the crew, which immediately presented to each on his arrival at the Airport along with flowers.
NETRACON Technologies has purchased another Tension Stringing Set for Twin Conductor formation stringing of 220 kV Chashma- Ludewala T/Line (Lot-II) alongwith 90 Stringing Blocks, Drum Lifters and allied Tools. All the Equipment has already been deployed on the site.
220 kV Grid Stations at Pull Khumeree & Mazar e Shareef have been completed , tested and commissioned on May5,2009 & May7,2009. Both the Grid stations were allotted to NETRACON by ABB Germany/WHG. The performance of NETRACON Technologies crews was hailed by Engr. Dirk Battige of ABB Germany. Mr. Dirk called Mr. Sherazi MD NETRACON and appreciated the dedication & excellent work of NETRACON as associates of ABB Germany.
With commissioning of 220 kV Link from Uzbekistan, Power is imported to Afghanistan. But it’s a matter of great pride that NETRACON Technologies have contributed quite appreciably to help KEC International to complete its most vital & tough sections in time as Sub Contractor to KEC International. Especially the towers in Sand Areas near Hairetan, Mountainous area of Khulm & Special Towers in Khulm are the works which gives an account of the hard work put in by the crews of NETRACON Technologies. To achieve timely completion of the far behind lagging project, Mr Sunder personally persuaded NETRACON to deploy its manpower on this section, who made it possible to complete the sections well ahead of the target dates.
Commissioning of 220 kVPull Khumeree–Chimtala T/Line completes and energizes the 220 kV Link from Uzbekistan. As such, Power is imported upto Kabul from Uzbekistan. NETRACON Technologies have considerable contribution to help KEC International to complete its toughest part of the T/Line passing through HinduKush Mountaneous Range and crossing over the sky high Salang Top. NETRACON accepted the challenge of completing Salang Top area alongwith Jabal Siraj areas of the T/Line. The unforgettable days of erecting towers at the altitude of 4000 M is an unforgettable feat of the NETRACON Tech Crews which were deployed on personnel persuanace of Mr. Sundar the then Country Manager Afghanistan (KEC Int’l.).Who regularly visited the ’warriors’ fighting the snow, chill & windy gusts on the top to inspire them and hail their efforts.